Connection to electricity grid (injection of electricity)

This LAP deals with:
• The grid connection agreements with electricity grid operators,
• The equipment required to connect the stationary fuel cell and to inject all produced or only surplus electricity into the grid,
• The qualification requirements for professionals entitled to carry out the connection works,
• The differences in treatment between the fuel cells micro-CHP and other comparable technologies.

Glossary:

Connection of the Fuel cell to the electricity distribution network with the possibility to inject electricity produced by the fuel cell.
As explained above, there are different possibilities of connection to electricity grid (injection)
• Stand-alone (no injection)
• Sell surplus electricity to the grid
• Sell all electricity to the grid

Pan-European Assessment:

There is no common EU framework for connection of stationary fuel cells to the electricity grids. In general, the connection procedures among partner countries require the conclusion of a connection (injection) agreements with the local/ regional electricity network operator. Each network operator has a model text for connection contract and number of templates to be filled in. The connection requirements are more general for all types of power generating units and are not specified for FC micro-CHP systems. In some countries for the signing of the connection agreement it is necessary to submit quite extensive technical documentation and even to carry out a feasibility study, which may cause additional costs and delays. The time needed for signing of a grid connection agreement vary widely among the partner countries and may take up to six months. Although, this is not seen as a significant operational or economic barrier to the market entry of stationary fuel cells, there is a need to simplify the administrative procedures and to reduce and adapt the required technical documentation and possible preliminary studies.
Is it a barrier?
Yes
Type of Barrier
Economic barriers, Regulatory gap
Assessment Severity
2
Assessment
Connection to the electricity grid may sometimes be very difficult based on the experience with RES in Bulgaria. Hydrogen specific legislation has to be in place as well as a favourable environment stimulation the industry. Nevertheless, there is industrial potential in Bulgaria as there is a lot of energy from RES (wind and solar). Also, involvement in demo project and publicity on the matter is neededUnclear duration for connection, high economic cost, lack of public and political awareness; FCs are not perceived as co–generation from a legal perspective

Questions:

Question 1 Agreement required? a) From whom? b) Model text? c) How much time does it take?
yes
Question 1 Agreement required? a - From whom?
a - Electricity distribution companies
Question 1 Agreement required? b - Model text?
b - yes, for CHP
Question 1 Agreement required? c - How much time does it take?
c - unspecified
Question 2 Requirement for additional equipment: a - all cases
a - n/a
Question 2 Requirement for additional equipment: b - additional requirements in case where all produced electricity is sold (injected)
b - n/a
Question 2 Requirement for additional equipment: c - additional Requirements in case when only surplus electricity is sold (injected)
c - n/a
Question 2 Requirement for additional equipment: d - additional requirements in case of self-consumption (no injection in the grid)
d - n/a
Question 3 Who can do the connection work (professional skills requirement)?
Qualified electriciton according to manufacturer's specifications and requiremenst or authorised company
Question 4 Technology to be compared with: Difference of treatment between the Fuel cells and the benchmark technology.
Cogeneration
Describe the comparable technology and its relevance with regard to hydrogen
Cogeneration