This LAP refers to the permitting process. It identifies what is the competent authority responsible for the permitting requirements, highlights the different steps of the process, and what are the different kinds of permits needed by the approval authority. Finally, it shows if the process is uniform throughout the country, how much time is needed to obtain the permit, and if there are some exemptions/simplified processes.
 
What is the competent authority responsible for the permitting requirements? If more than one, list them
What are the different steps of the process? Please indicate which authority in charge of which step if different authorities are involved
Are there any exemptions/”simplified” process (e.g. for demonstration projects)?
What kind of permits are needed by the approval authority, and are they separated/integrated (single permit)? E.g. building permit , construction and operation permit for installations, environmental permit
Is the process at local level uniform throughout a country? (uniform interpretation?)
How long does it take to obtain a permit for the construction and operation of a hydrogen production facility? a
) Is there a maximum response time for granting the permit b) If yes, what is the response time? c) What is the experience in practice?
a - Is there a maximum response time for granting the permit
b - If yes, what is the response time?
c - What is the experience in practice?
Is it a barrier? Yes
Type of Barrier Economic barriers
Assessment Severity
2
Assessment On safety requirements:
Specific H2 detection equipment have to be permanently installed on the production site to monitor the H2 concentration in the atmosphere (if the production is packaged or in–door). The personnel has to be equipped with a mobile H2 detection system for specific maintenance operations, control operations after an accidental shut–down of the unit, restart of the unit etc. The staff needs to be trained on H2 safety & operation
View Legislation Table
PDF Export | Excel Export
The information is correct There are errors ...
Submit a suggestion for improvements
This map depicts the severity of this barrier across the HyLaw Partner countries.
  •   No barrier
  •   Low
  •   Medium
  •   High
  •   Data not available
  •   Selected countries